Switchboard RFQ Checklist: What to Send for a Fast, Accurate Quote

Buyer Guides

Switchboard RFQ Checklist: What to Send for a Fast, Accurate Quote

Most switchboard quotes are slow because the request is missing three or four facts. This checklist lists everything a panel builder needs, in the order engineers read it.

SEGA M Engineering Team
Updated 6 Nov 20266 min read
SEGA M technician assembling busbar connections inside a low-voltage switchboard

When a request for quotation arrives complete, a panel builder can price it in days. When it arrives as one drawing and a line saying "please quote", the first week goes on questions and answers. This is the checklist our engineers would like every customer to have. Use it for SEGA M or for any other supplier: a complete RFQ gets you comparable offers.

1. Drawings and lists

  • Single-line diagram (SLD) for every board, with incomer, bus couplers and every outgoing feeder. This is the one document we cannot quote without.
  • Bill of quantities (BOQ) with the number of each board and any spare feeders.
  • Specification or the electrical section of the tender documents.
  • Room layout, if space is tight: available width, depth, height and door sizes on the way in.

2. Electrical ratings

  • System voltage and frequency (for example 400 V, 50 Hz) and the earthing system (TN-S, TN-C-S, TT, IT)
  • Rated current of the main busbar and incomer
  • Prospective short-circuit current at the board (kA) and for how long (usually 1 s)
  • Rating and type of each outgoing feeder: MCB, MCCB, ACB, fuse switch, motor starter
  • Any metering, power analysers, power factor correction or automatic transfer (ATS)

If the fault level is not known yet, tell us the transformer size and impedance and the cable length from the transformer, and we will estimate it.

3. Construction

  • Standard: IEC 61439-2 for power boards, IEC 61439-3 for small distribution boards. See our IEC 61439 guide.
  • Form of internal separation, from Form 1 to Form 4b. See forms of separation explained.
  • Degree of protection (IP) and impact (IK), indoor or outdoor
  • Free-standing, wall-mounted or recessed; front-only or rear access
  • Cable entry from top or bottom, and cable sizes for the incomer
  • Fixed, plug-in or withdrawable units
  • Colour (RAL 7035 is our standard) and labelling language

4. Preferred brands

Many specifications name the brand of breakers and devices. Tell us if a brand is required, preferred or open. If it is open, we can offer options at different price levels.

5. Site conditions

  • Maximum ambient temperature in the room, not the outdoor average
  • Altitude, if above 1,000 m
  • Humidity, dust, salt air (coastal sites) or chemicals

Hot sites in Africa and the Gulf often need derated busbars or ventilation. Telling us early avoids a redesign later.

6. Commercial details

  • Delivery place and Incoterm (EXW, FOB, CIF or delivered). If you do not know the nearest port, we quote to a port we select and re-quote to another on request.
  • Required delivery date and whether partial shipments are allowed
  • Documents needed: test reports, certificates of origin, approvals
  • Whether you want to attend the factory acceptance test (FAT)

Ready to send?

Send your SLD and BOQ through our contact form or to export@sega-m.com. SEGA M builds SIVACON S8 switchboards as a Siemens Advanced Partner, its own type-tested MFB and NSFB boards, and metal enclosures up to IP65, all in our 30,000 m² factory in 10th of Ramadan City, Egypt. Standard items ship from stock, and larger projects typically take up to 6 weeks; the exact time is confirmed in our offer.

Frequently asked questions

What is the minimum I need to send for a switchboard quote?

A single-line diagram, the quantities, the system voltage and the fault level. Everything else can be agreed with our engineers.

I don't know the short-circuit level. Can you still quote?

Yes. Send the transformer rating and impedance and the cable length, and we will estimate the fault level.

How long does SEGA M take to deliver a switchboard?

Standard items ship from stock. Larger projects typically take up to 6 weeks; the time is confirmed in each offer.

Can we witness the factory test?

Yes. Customers are welcome to attend the factory acceptance test in 10th of Ramadan City.